Kalyan’s Patripool ROB ready for inaugurationIllustrative image – not actual.
The work of the new Kalyan’sPatripool Rail Over Bridge (ROB) has been completed and will be thrown open to public on 25 January 2021. 
 
The ROB will be inaugurated by Maharashtra Chief Minister Uddhav Thackeray through video conference. 
 
The bridge has the longest 76 mtr web link girder in the entire Mumbai Metropolitan region. Apart from the longest web link girder, the bridge also has another girder of 33 mtr. Both these girders were built in Hyderabad, Telangana. 
 
Usually, it takes eight months to build a girder, but considering the need of the bridge, the girders were built in two-three months. 
 
The girders were built with a welding work of 25 km length and it has around 30,000 nut bolts and 45,000 connection holes. The entire bridge weighs around 850 tonne. 
 
The major reasons for delay were designing the bridge, approvals, opposition from residents and the COVID-19 pandemic.
 
The 104-year-old bridge was dismantled in an emergency after it was declared unsafe by IIT Bombay without any plan ready for the new bridge. The planning and designing were done and approval was sought later on. 
 
When the work commenced, the authorities realised that a drainage chamber was blocking the work, so the bridge was redesigned leading to a delay.
 
MSRDC took up the work of the new Patripool bridge in December 2018, two months after it was dismantled by the Central Railway. During the lockdown, work at the site was completely stalled as the labourers deployed for work left for their hometown. 
 
The work on the project gained speed since May 2020 after the nodal agency decided to utilise the lockdown period.
 
Apart from the newly-built two-lane bridge, an additional two-lane bridge will be built considering future requirement of traffic movement on this route. The work of the girder for the additional bridge has already begun.