Illustrative image – not actual.The first unit of the Kaiga nuclear power project commenced commercial power generation on 13 October 2000. The reactor of the 220 MW power plant was activated on 26 September 2000.
The second unit of 220 MW of the Kaiga project was synchronised to the grid on 1 December 1999, before the completion of the first. The completion of the first unit was delayed because a portion of the inner dome’s undersurface had collapsed on 13 May 1994.
The entire project of 2x220 MW is now complete -- albeit with a cost overrun of around Rs.2,200 crore (around three times the initially estimated cost) and a time overrun of nearly five years.