Illustrative image – not actual.K M Sugar's expansion plan at its Motinagar unit in the district of Faizabad district of Uttar Pradesh will be completed by December 2007 and will be ready by the next crushing season.
K M Sugar Mills is expanding its sugar capacity from 6,000 tccpd to 7,000 tccpd at Motinagar at an estimated cost of Rs.650 million. In addition, the company has embarked installation of 20 MW cogen unit at an estimated cost of Rs.550 million . The company has completed the installation of cogen unit in March 2007.
Avant Garde Engineers & Consultants Pvt. Ltd is the consultant for the project and machinery for the project have been supplied by Triveni Engineering.