Illustrative image – not actual.The ramp-up will be implemented in phases. In Phase-I, JSW will revamp and restart electric arc furnace andt slab caser and modernise the hot strip mill.
The proposed investment, including the cost of acquisition, is expected to be around USD 250 million.
In Phase-II, depending upon economic viability and prevailing market conditions, JSW will evaluate the possibility of adding another electric arc furnace as well as additional manufacturing equipment at the hot strip mill to make the Ohio facility a fully integrated unit, with three million tpa capacity.
The proposed investment in Phase-II will be in the range of up to USD 250 million, subject to feasibility studies and necessary approvals.