Illustrative image – not actual.JSW Energy is relocating its proposed 2,400 MW imported coal based power project to Dahej in Bharuch district of Gujarat.
Earlier, JSW planned to set up the power project at Simar in Junagadh district of Gujarat. It is learnt that, the project has been shifted due to the lack of proximity to the port.
The Rs 4,800 crore project is to be implemented in two phases. In Phase I two units of 800 MW is to be set up, while Phase II will have one unit of 800 MW capacity.
Tata Consultancy Engineers have conducted the pre-feasibility study and DPR has been in place. Toshiba JSW Steam Turbine Generation is likely to supply turbines for the project.
JSW Energy has applied for coal linkages, land allocation and water supply. Work on the project is slated to commence by March 2010.
Also See:
JSW Energy takes up two mega thermal power projects (11-May-09)
Related Links:
Project profile