Illustrative image – not actual.
JSW Renew Energy Five (JSW Renew Five), a wholly-owned subsidiary of JSW Neo Energy has inked a battery energy storage purchase agreement (BESPA) for the first project of 250 MW/500 MWh standalone battery energy storage system, out of the total awarded project capacity of 500MW/1,000MWh (two projects each of 250 MW /500 MWh) with Solar Energy Corporation of India (SECI).
The company will be entitled to receive a fixed capacity charge of Rs 10.84 lakh per MW per month for twelve years for 60 percent of the total capacity, amounting to 150MW/300 MWh. The project is required to supply power of the contracted capacity in a period of 18 months.
The remaining 40 percent of the project capacity, i.e.,100 MW/200MWh is to be managed by the company.
JSW expects to have 9.8 GW of operational generation capacity by CY 2024, and aims to reach 20 GW generation capacity and 40 GWh of energy storage capacity before 2030. JSW Renew Five is a step-down subsidiary of JSW Energy.