JSW Energy, on 16 October 2011, commissioned the 300 MW Unit IV of its power plant at Ratnagiri in Maharashtra.


With this, the entire 1,200 MW coal based power plant is now fully operational and is supplying uninterrupted power to the state grid. This apart, the company, 12 October 2011, resumed operations of 2 X 135 MW Barmer power project pursuant to the grant of adhoc interim tariff by Rajasthan Electricity Regulatory Commission (RERC), using lignite from the Kapurdi reserves. The lignite mining by Barmer Lignite Mining Company (BLMCL) has commenced operation upon the transfer of mining licence for Kapurdi reserves in favour of BLMCL.