Illustrative image – not actual.JSW Dharamtar Port has obtained terms of reference (ToR) from the Ministry of Environment, Forest and Climate Change (MoEF&CC) for its proposed project, Phase-II-A expansion of Dharamtar Jetty Facility at village Beneghat/ Dolvi in Raigad district, Maharashtra.
The project will handle various liquid and solid cargo. Phase-II-A involves handling third-party cargo of five million tpa, including various liquids such as edible oil, lube oil, furnace oil, bitumen and any other liquid cargo and bulk cargo such as fly ash, sand and aggregates, gypsum, salt, fertilizers, bauxite, sugar, tiles, food grains, pulses, mill scale, project cargo, and any other bulk/break bulk solid cargo in the developed infrastructure of the jetty facility.
The jetty backup facility for transient storage for Phase-II over 53 ha is nearing completion.
The backup for the proposed diverse, third party cargo will be laid out over a 31 ha jetty backup land which was earmarked for Phase-III expansion of the jetty facility.
An additional berth of 120 mtr may be constructed for bunkering the barges, depending on requirement of quay based on berth occupancy rate.
The estimated cost of the project is Rs 500 crore. It will create direct jobs and secondary opportunities.
The expansion of Dharamtar Jetty Facility from 8.24 million tpa of cargo, 331.5 mtr jetty to 16.89 million tpa cargo, 1,050 mtr total jetty length under Phase-II and 33.95 million tpa cargo, 1,750 mtr total jetty under Phase-III is currently underway.
The main commodity to be handled at the facility after the expansion includes IBRM, CBRM, fluxes, clinker, cement, steel sheet, among others.