Illustrative image – not actual.Jindal Steel and Power (JSPL) is likely to complete two of its steel projects in the next 30 months. The plants coming up in Orissa and Jharkhand will entail a total investment of Rs 44,000 crore.
The Rs 23,000-crore steel plant at Angul in Orissa will have an annual production capacity of six million tonne, of which three million tonne will be commissioned by end-2011 as part of Phase I.
The Phase I of the Jharkhand project having three million tpa capacity will commence production by the end of 2012. The project will cost Rs 21,000 crore.
Land acquisition for both the projects has been completed with 5,000 acre at Angul in Orissa and 3,000 acre in Jharkhand. Also, financial closure for the Angul project has been achieved, while for the Jharkhand project it is awaited.
Also See: