JSPL completes expansion project ahead of scheduleIllustrative image – not actual.

Jindal Steel & Power has successfully completed its overall expansion project at Raigarh in Chhattisgarh. The Rs.550 crore expansion project was launched in May 2004.

The project has resulted in JSPL's sponge iron capacity rising by 7.2 lakh tpa, power by 50 MW and steel melting by 7.5 lakh tpa. The project also envisaged setting up of a coal washery with capacity 3.5 million tpa.

The project was completed as per the following schedule.

Facility Units Incremental
Capacity
Scheduled Completion Actual
Completion
Phase I
Sponge Iron (Kiln 1) lakh tpa 1.8 Mar-05 Sep-04
Sponge Iron (Kiln 2) lakh tpa 1.8 Mar-05 Jan-05
Power Plant MW 25 Mar-05 Sep-04
Coal washery million tpa 3.5 Mar-05 Mar-05
Phase II
Sponge Iron (Kiln 3) lakh tpa 1.8 Sep-05 Mar-05
Sponge Iron (Kiln 4) lakh tpa 1.8 Sep-05 Mar-05
Power Plant MW 25 Sep-05 Mar-05
Steel Melting Shop lakh tpa 7.5 Sep-05 Mar-05

The final capacity of the Raigarh plant now stands as follows:

Facility Units Capacity
Coal washery million tpa 3.5
Sponge Iron lakh tpa 13.7
Steel Melting Shop lakh tpa 75
Power Plant MW 265