Illustrative image – not actual.Jindal Steel & Power has successfully completed its overall expansion project at Raigarh in Chhattisgarh. The Rs.550 crore expansion project was launched in May 2004.
The project has resulted in JSPL's sponge iron capacity rising by 7.2 lakh tpa, power by 50 MW and steel melting by 7.5 lakh tpa. The project also envisaged setting up of a coal washery with capacity 3.5 million tpa.
The project was completed as per the following schedule.
| Facility | Units | Incremental Capacity |
Scheduled Completion | Actual Completion |
| Phase I | ||||
| Sponge Iron (Kiln 1) | lakh tpa | 1.8 | Mar-05 | Sep-04 |
| Sponge Iron (Kiln 2) | lakh tpa | 1.8 | Mar-05 | Jan-05 |
| Power Plant | MW | 25 | Mar-05 | Sep-04 |
| Coal washery | million tpa | 3.5 | Mar-05 | Mar-05 |
| Phase II | ||||
| Sponge Iron (Kiln 3) | lakh tpa | 1.8 | Sep-05 | Mar-05 |
| Sponge Iron (Kiln 4) | lakh tpa | 1.8 | Sep-05 | Mar-05 |
| Power Plant | MW | 25 | Sep-05 | Mar-05 |
| Steel Melting Shop | lakh tpa | 7.5 | Sep-05 | Mar-05 |
The final capacity of the Raigarh plant now stands as follows:
| Facility | Units | Capacity |
| Coal washery | million tpa | 3.5 |
| Sponge Iron | lakh tpa | 13.7 |
| Steel Melting Shop | lakh tpa | 75 |
| Power Plant | MW | 265 |