Jindal Steel & Power has successfully commissioned the 351 cubic metre (m3) blast furnace at Raigarh district of Chhattisgarh within 16 months from zero date.

 

The design of the blast furnace was based on the latest technology and is fitted with stave cooling, cast house, hot blast stoves, gas cleaning system, blowers, slag granulation unit, conveyorised charging system, stock house with electronic weighing system and all other service facilities. The blast furnace has also been provided with PLC-based control & monitoring system for furnace charging and hot blast stoves. The advanced features would help in high productivity and less energy consumption.

 

Mecon was the project management consultant for the blast furnace.