Illustrative image – not actual.JSL, the stainless steel company, plans to come out with a rights issue in a span of two months to raise Rs 500 crore to part-fund its Orissa project.
The company is looking to issue around 70 million shares to its existing shareholders, which will strengthen the promoter's stake by about 4 per cent in the firm to 60 per cent.
JSL is undertaking a Rs 5,600 crore capacity expansion programme in the Phase II of the Orissa project to set up an 800,000 tpa mill to produce the alloy. JSL has raised about Rs 4,400-4,500 crore in debt for the Phase II expansion.
The company has already installed a 250 MW power plant, a 200,000 tpa ferro-alloy mill along with a 425,000 tpa coke oven unit in Phase I of the project. Along with its current 700,000 tpa stainless steel mill in Hissar, Haryana, it aims to reach an overall production capacity of 1.5 million tpa by March 2012.