Power Co's 120 MW Jojobera power plant is scheduled for commissioning in record
time of 24 months. Bharat Heavy Electricals, the EPC contractor for the Rs.400
crore project, has stated that the plant would be synchronized to the grid on 31
August 2005 and commercial production will begin by end-October 2005.
The Tiruchi unit of BHEL undertook design, fabrication and manufacturing, besides installation and commissioning of the project. BHEL's contract value was worth Rs.188 crore. TCE Consulting Engineers was also associated with the project, with a service scope comprising project designing, procurement assistance, inspection of equipment, etc.
The Jojobera power plant already has three units -- 1 x 67.5 MW and 2 x 120 MW -- aggregating 307.5 MW. On completion of the project in question (fourth unit), the power plant's capacity would stand enhanced to 427.5 MW. The power plant is located in Singhbhum district of Jharkhand, 10 km from Tata Steel's Jamshedpur complex.
Brief History: Tata Iron & Steel Co commissioned the Jojobera plant -- then with one unit of 67.5 MW -- on 13 January 1996. In 2000-01, Tata Power acquired the plant from Tata Steel for a consideration of Rs.300 crore. Subsequently, TPC undertook capacity expansion in stages, in the form of additional power units of 120 MW each. The Jojobera plant supplies power to industrial units in Jharkhand, including Tata Steel. Incidentally, BHEL was the EPC contractor for the first unit of 67.5 MW. This project was completed in 50 months, which was also a record during that time.