Illustrative image – not actual.Jawaharlal Nehru Port Trust has appointed Scott Wilson, as project management consultant (PMC) for its Rs.800 crore channel deepening and widening programme.
Scott Wilson will be advising the port on global tenders and bidding process for dredging project that is likely to be completed by December 2008.
In September 2005, Cabinet Committee on Economic Affairs (CCEA) approved the port's channel dredging project involving a direct capital cost of Rs.670 crore, a financing cost of Rs.58 crore and Rs.71 crore as contingency expenses.
The major portion of project cost would be met
through internal resources and remaining would be raised from the market.
The bidding process followed by tendering will take six months and we are
expecting to award the project by mid-2006. The dredging work is likely to be
completed in 27 months.
Under the first phase, the channel will be dredged up to 14m from the current 12.5m, and it will further be dredged up to 16m in the second phase. The second phase with an estimated cost of Rs.1,210 crore is still under the planning stage.
To accommodate larger and direct mother vessels, it is also being planned to widen the existing main harbour channel and JN Port approach channel to 370m for straight reach and 450m at bend and at port berths.
The Union finance ministry is likely to reschedule Rs.727 crore dues from the port to the government.
However, the government has refused equity participation in the project and asked the port to raise money on its own.
Currently, JNPT could handle vessels having draught up to 12.5m only making use of tidal window. But with its channel dredged up to 14m, this major port could handle larger vessels of 6,000 TEUs capacity.
Also See:
JNPT channel deepening project approved (23-Sep-05)