Illustrative image – not actual.Jindal Vijaynagar Steel plans to advance the commissioning of its 3.3 million tonne pellet plant from December to October 2000 and postpone the commissioning of the second phase of the Corex steel plant (Corex II) from December 2000 to February 2001.
The reason behind this move being that disbursals of Rs.40 crore for the pellet plant have already been received while the Rs.50 crore required for the Corex II plant have yet to come in.
For the completion of the pellet plant, the company would now source the necessary two million tonnes of fines from private firms. Earlier, the company had planned to source the same from Vijaynagar Minerals, but this unit is yet to receive clearance from the Union Ministry of Environment and Forests.
The company’s project involves setting up of the Corex steel plant in two phases with an investment of Rs.6,144 crore and a pellet plant with an investment of Rs.429 crore. Both these units were coming up at Bellary in Karnataka.