Illustrative image – not actual.Jindal Vijaynagar Steel singed a
MoU with miners, near its captive mines in Bellary in Karnataka, for the supply
of iron ore fines. This is because the company’s captive mines, which have not
been cleared by the environment authorities, have not yet begun operations. The
fines sourced from these miners would be used by the company’s Rs.430 crore,
three million tonne pellet plant, which would commence operations in October
2000. The company planned to retain half the produce of this plant for captive
use and export the other half.