Illustrative image – not actual.Jindal
Strips Ltd has decided to go ahead with
its 1 million tonne per annum (tpa) stainless steel project at Duburi in Jajpur
district of Orissa. This was stated by Mr N K Taori, President for the Orissa
project. The following is a brief account of the Rs.4525 crore project, that
would be implemented in two phases.
Phase I: The first phase, costing Rs.775 crore, would involve the setting up of a 1.5 lakh tonne ferro chrome plant and a smelting unit to process 0.5 million tonnes per annum of stainless steel. The project would come up on a 500 acre expanse of land at Duburi in the Jajpur district of Orissa. The ferro chrome plant will have a gestation period of 15 months, and the smelting shop, 30 months.
Phase II: In the second phase, costing Rs.3,750 crore, a captive power plant of 240 MW will be set up at Talcher. Besides, facilities for hot and cold rolled products will be installed. The capacity of the stainless steel unit will be enhanced to 1 million tonnes, by setting up a sponge iron plant and also a coal-based blast furnace using iron ore. These units would come up on 1,000 acres of land adjacent to the Phase I location.
Change in Scope
The
project scope has undergone some change since it was last announced. Earlier
the capacity of the stainless steel plant was proposed to be 1.8 million tpa.
Besides, a ferro chrome unit, of 6 lakh tpa, was proposed, as against 1.5 lakh
tpa. The downward revision in the ferro chrome unit capacity is mainly due to
problems faced in acquiring mining rights at the ferro chrome deposits at
Tangarpada in Dhenkanal district.
Status
(As of 11 May 2003)
Land:
The company has paid Rs.1.56 crore
to Infrastructure Development Corporation Orissa (IDCO), out of the total cost
of Rs.6 crore. The land would be handed over during May 2003.
Consultant:
Mecon has been appointed consultant
for the project. The final land layout of the project is expected on 19 May
2003.
Power:
The company has approached Grid
Corporation of Orissa to allot 150 mva of power through a 220 kv line from the
new sub-station at Duburi. This is for the first phase of the project. Power
allocation would be enhanced to 300 mva in the second phase. Besides, power
would also be sourced from the captive power plant.