Illustrative image – not actual.Jindal Stainless Ltd, part of the OP Jindal group, has finalised plans of setting up a greenfield stainless steel complex in the Kalinga Nagar Industrial Complex in Jajpur district of Orissa.
The Rs.4,100 crore project would be implemented in two phases costing Rs1,100 crore and Rs.3,000 crore respectively. In the first phase, JSL would set up a 1.6 lakh tpa ferro chrome facility and a stainless steel manufacturing facility with capacity 8 lakh tpa. This phase is targeted for completion by end-2006.
In Phase II, the ferro chrome facility would be expanded to 4.8 lakh tpa, stainless steel capacity would be doubled to 16 lakh tpa and a 500 MW coal-based power plant would be set up. In nominal terms, this phase would cost Rs.3,000 crore and is scheduled for commissioning by end-2008.
The project would be sourced through internal accruals, domestic and international borrowings, and fresh equity. The company's present equity capital is Rs.19 crore, which is likely to be enhanced considerably to match the size of operations.
So far, the company has committed Rs.200 crore towards the project, largely in the form of advance payments to suppliers. Besides, coal linkages for the proposed power plant have also been firmed up.
JSL has a 40 per cent share in India's stainless steel market.
The project was first proposed in May 2003. The scope of the project has undergone some change, mainly pertaining to downscaling of ferro chrome production capacity.