Illustrative image – not actual.The first phase of Jindal Power's 1,000 MW Raigarh power project in Chhattisgarh has attained financial closure. As against the required debt of Rs.1,500 crore, the project has received commitments for over Rs.2,300 crore for Phase I comprising two units of 250 MW each. Loans would have a 12-year tenure and a coupon rate of 8 per cent.
The first unit of 250 MW will be commissioned by March 2007. Thereafter, one unit of like capacity will be commissioned at an interval of three months each. The full project will be commissioned by end-2008.
The funds required for Phase I are estimated at Rs.2,142 crore comprising 70 per cent debt and 30 per cent equity. The entire equity component (Rs.642 crore) has been brought in by the promoters.
JPL will sell 350 MW worth of power to a large industrial estate being developed by the company, 15 km from the plant site. Details on the industrial estate project are awaited.