Illustrative image – not actual.The Reliance Power has sold off 4,000 MW Ultra Mega Power Project (UMPP) in Tilaiya to Jharkhand Urja Vikas Nigam.
The company has transferred its entire holding of 1,49,900 equity shares of Rs 10 each, aggregating to Rs 14,99,000 held in Jharkhand Integrated Power a special purpose vehicle (SPV) created for development of Tilaiya UMPP, to Jharkhand Urja Vikas Nigam.
Reliance Power had won contract for the project in 2009 at a record low tariff of Rs 1.77 per unit. The company has sold the special purpose vehicle (SPV) formed to execute the project to Jharkhand Urja Vikas Nigam (JUVNL) for Rs 1.12 billion.
The company had exited the project in 2015, citing delay in land acquisition. The SPV -- Jharkhand Integrated Power (JIPL) -- terminated the power purchase agreement (PPA) of its Tilaiya UMPP in Hazaribagh district with 18 power off-takers in 10 states for 25 years.
Reliance Power has also received bank guarantee worth Rs eight billion from the 10 states it had signed the PPA with. Besides Jharkhand, Gujarat, Delhi, Punjab and Haryana were among the states with which the company had signed 25 year contracts for power supply.
The company had planned capital expenditure of Rs 360 billion for the project, and the Kerandari coal block in the North Karanpura coal fields in Jharkhand was allotted to it for the project.
The Jharkhand government, after a delay of five years, had allotted 470 acre of forest land to the company in 2015 and was in the process of allotting another 1,220 acre by 2016.