Illustrative image – not actual.The tendering for building the highway was done in 2017, and in early 2018 K K Builders bagged an order worth Rs 45.95 crore for renovating the road. As of March 2018, two percent of the highway work was completed.
As per the latest information available with Projects Today, the renovation work is progressing well and in the duration of two months around 20 percent of the highway work was completed. The project is expected to get over by the end of 2019 instead of the earlier completion date of April 2019.