Jeet Metals' copper products unit relocated to BareillyIllustrative image – not actual.

Jeet Metals' has relocated its proposed 400 tpd copper products facility from Aligarh to Bareilly in Uttar Pradesh. The location of the project was changed due to non-allocation of required land for the project.

Land acquisition of required 400 acre to set up the plant is underway and is likely to complete by November 2009. The relocation process has increased the cost of the project from Rs 1,500 crore to Rs 1,800 crore.

The unit is expected to manufacture copper rods, pipes, billets, sheets, strips and castings. The project is likely to be completed by October 2010.