Illustrative image – not actual.Maharashtra State Electricity Transmission Co. (MSETCL) has arranged a Rs.626.43 crore loan from the Japan Bank for International Co-operation (JBIC) for replacement of transformers.
The project will cover 15 districts of western Maharashtra, the Konkan and Khandesh. The loan will be repaid in 30 years and the interest rate will be 1.3 per cent per annum. The loan agreement will be signed by August 2007.
MSETCL plans to replace 18 existing transformers in 110 sub-stations to raise capacity by 6,675 MVA. Preliminary agreement on the funding plans was signed on 1June 2007 by MSETCL .
Earlier, the transformers were planned to be replaced over a period of five years. MSETCL now seeks to replace them on a fast-track basis within three years (before March 2010), with the help of the assistance from JBIC.