Illustrative image – not actual.A review meeting was held on 03 April, 2026 to assess progress on the Bhama Askhed water supply project, attended by Pimpri Chinchwad Municipal Corporation (PCMC) PCMC Commissioner Dr. Vijay Suryawanshi, BJP MLA Mahesh Landge, Leader of the House Prashant Shitole, along with senior officials.
The discussion focused on the status of various components of the project, which is designed to bring 167 million litres per day (MLD) of water from the Bhama Askhed dam to Pimpri-Chinchwad, enabling a shift from alternate-day to daily water supply. According to civic officials, key infrastructure is progressing: the jackwell is fully complete, the pump house is 75 percent done, the substation is 80 percent complete and the approach bridge stands at five percent completion. All electrical, mechanical, instrumentation and SCADA materials are fully available. MLA Landge raised serious concerns about pollution at the Ravet and Nighoje barrages, and urged implementation of advanced tertiary treatment systems. He also emphasized the need to speed up the Nigdi augmentation Phase-II project and expand the Nigdi water treatment plant’s capacity from 428 MLD to 528 MLD to meet growing demand.
MLA, Mahesh Landge, informed, “An experienced officer from the revenue department and the municipal establishment should be appointed full-time to handle land acquisition and required permissions for the water supply project. The Andra–Bhama Askhed project is extremely important for Pimpri-Chinchwad. The project will be fully operational by January 2027 under any circumstances. We are continuously following the project up under the guidance of Chief Minister Devendra Fadnavis."