Illustrative image – not actual.According to the Union Minister of
Petroleum & Natural Gas, Mr. Ram Naik, the Jamnagar-Loni pipeline would be
commissioned by December 2000 ahead of the scheduled commissioning date of
February 2001. GAIL has already commissioned the first dispatch terminal of the
pipeline in August 2000.
The 1,230 km long pipeline, which
is estimated to cost Rs.1,250 crore, would have an initial capacity of 1.7
million tonnes per annum. This capacity would be increased to 2.5 million
tonnes by 2011-12.
The Jamnagar-Loni pipeline will
traverse five states, viz. Gujarat, Rajasthan, Haryana, Delhi and Uttar
Pradesh. The pipeline will carry LPG from the Reliance and Essar refineries in
Jamnagar and Indian Oil Corporation’s (IOC) import terminal at Kandla, for IOC,
Bharat Petroleum Corporation and Hindustan Petroleum Corporation.