Illustrative image – not actual.The ropeway project in Jammu is likely to be completed by the end of 2019 and will be thrown open to the public. The project has previously missed several deadlines.
The 1.66 km long cable car project has two phases, the first from Bahu Fort to Mahamaya Park and the second from Mahamaya to Peer Kho over Tawi river, with a total length of 1,118 mtr.
The ropeway from Bahu Fort to Mahamaya has eight cabins and from Mahamaya to Peer Kho 14 cabins and the total number of towers in section one (Peer Kho to Mahamaya) and section two (Bahu Fort to Mahamaya) are nine and the critical component are all imported. The estimated cost of the project is Rs 75 crore, out of which 85 percent of the total cost has been incurred so far.
The project was planned in 1995, and was to be operated from Bahu Fort to Mubarak Mandi Complex initially. It was modified and relocated when Mubarak Mandi and Bahu Fort were declared protected monuments. The cable car corporation successfully conducted the trial run of Phase-I in April 2018.