Jal Power still to award E&M contract for Rangit HEPIllustrative image – not actual.

Jal Power Corporation is yet to award electro-mechanical (E&M) contract for its hydel based power project in West Sikkim.

The company has not yet completed the modalities for the award of the balance of plant (BoP) components of the 120 MW Rangit-IV hydro electric power project (HEP) in West Sikkim.

In August 2009, the company had invited bids for the package. It had received five bids in November 209. However, the company is yet to select a contractor from amongst Siemens, L&T, ABB, Andritz Hydro and EdCIL.

So far, the company has completed the excavation of Adits 1 and 2. Further, 49,000 cubic mtrs of excavation of the dam, out of 1,56,000 cubic mtrs, has been completed, while the excavation of road diversion tunnel has been fully completed. Excavation of head race tunnel in about 960 mtrs out of the total 6,488 mtrs has been completed.

The project proposes to utilise the tail water of Rangit Stage-III HEP as well as the discharge of the Kalej-Khola, a major tributary of Rangit river. The estimated cost of the project is Rs 726.17 crore and it is scheduled to be commissioned during the XIIth Plan period, in the year 2012-13.