Illustrative image – not actual.The joint venture between DS Constructions and
Jaiprakash Associates (part of Jaiprakash Industries Group) may bag the 8/6
lane Delhi-Gurgaon
expressway project on NH-8.
The 26 km project is estimated to cost Rs.400 crore and
would be developed on a build, operate and transfer basis under the direct
tolling method.
The DS Constructions-Jaiprakash Associates consortium
has emerged as the lowest bidder for the project. The other companies that
submitted financial bids for the project include Gamuda, IJM, RBM (all from
Malaysia) and Larsen & Toubro.
The project envisages a capital grant to be paid by
NHAI to the successful bidder towards the cost of construction for enhancing
the viability of the highway project. However, the consortium had indicated in
its financial bid that it was willing to return about Rs.60 crore to NHAI out
of the total capital grant.
The highway operator would be allowed to collect
tolls from users during the concession period at the rates notified by the
Union Government to recover capital costs, operating expenses of the project
and the returns thereon.
This will be the first access-controlled expressway
project to be implemented by NHAI with private sector participation.