Illustrative image – not actual.IVRCL Infrastructure of India has restarted work on Rahughat Hydropower Project in Nepal after receiving compensation from Nepal Electricity Authority (NEA).
The company had secured a contract worth $31 million (approx Rs 192.2 crore) for the project in December 2010. As per the contract, the contractor had to start work in December 2012, which was supposed to be completed in 42 months. Due to a delay in the appointment of a consultant by NEA, IVRCL was unable to start work on the project.
After the consultant was appointed, the contractor applied for compensation citing rise in prices of construction materials because of the delay. The contractor started civil work this week after receiving payment of Rs 3.93 crore as compensation from NEA.
The project, with 32 MW capacity, is located in Myagdi district and is developed with soft loan worth US$ 67 million (approx Rs 415.4 crore) from Exim Bank of India. It is expected to be completed by June 2018.
The IVRCL has already commenced work on a construction camp, crushing plant and security camps. The contractor is also making preparations to build an access road and a 6-km tunnel.