IVRCL Infrastructures & Projects Ltd has secured orders to the tune of Rs.368.14 crores in total.

Chennai Metropolitan Water Supply & Sewerage Board awarded : (project details)

  • Water distribution station at Kilpauk in Chennai for storage & pumping station of drinking water including civil, electrical, mechanical & instrumentation. (contract value: Rs.56.27 crores)
  • Water distribution station at K.K Nagar in Chennai for storage & pumping station of drinking water including civil, electrical, mechanical & instrumentation. (contract value: Rs.26.12 crores)
  • Pipeline for conveyance of desalination product water (Package-I), i.e.22 kms of 1000 mm ductile iron pipeline, supply laying and jointly including all related appurtenances and civil works. (contract value: Rs.50 crores)
  • Pipeline for conveyance of desalination product water (Package-II), i.e 12 kms of 900 mm ductile iron pipeline, supply laying and jointly including all related appurtenances and civil works. (contract value: Rs.29 crores)

Tamil Nadu Water Supply & Sewerage Board awarded :

  • Water supply in Tsunami affected areas in Kanyakumari district funded by ADB, includes 55 kms of PSC pipeline with elevated & ground level storage reservoirs, pumping stations including electrical mechanical & instrumentation. (contract value: Rs.29 crores)
  • Combined water supply scheme Aranthangi in Pudukottai district, includes 109 kms of PSC pipeline with elevated & ground level storage reservoirs, pumping stations including electrical mechanical & instrumentation, appurtenances. (contract value: Rs.38.88 crores)
  • Water supply improvement scheme Tambaram Municipality in Chennai, includes 49 kms of DI pipeline with elevated & ground level storage reservoirs, pumping stations including electrical mechanical & instrumentation, appurtenances. (contract value: Rs.32.22 crores) (project details)

NTPC Tamilnadu Energy Company Ltd awarded : (project details)

  • Ground improvement by installation of stone columns at 2x500 MW thermal power plant of NTPC-TNEB at Ennore near Chennai that includes 420000 RMT of stone columns to installed in 12 months and 28 lakh cubic mtrs of filling with flyash, gravel, earth. (contract value: Rs.93.65 crores)
  • Providing fencing and boundary wall at 2x500 MW thermal power plant of NTPC-TNEB at Ennore near Chennai. (contract value: Rs.13 crores)