ITD Cementation India to complete road projects in Punjab and Jammu & KashmirIllustrative image – not actual.

ITD Cementation India is likely to complete work on two road projects in Punjab and Jammu & Kashmir by December 2011, as told to ProjectsToday.

 

The company has completed around 90 per cent work on the NHAI’s four laning of Pathankot-Jammu section on NH-1A in Gurdaspur district of Punjab and Jammu & Kashmir. Also, it has completed 95 per cent work on another NHAI project of four laning of km 70 to km 110 of Bhogpur-Pathankot section (NS-37/PB) of NH-1A in Hoshiarpur and Gurdaspur district of Punjab. The project value is estimated at Rs 309 crore and Rs 286.69 crore respectively.

 

Meanwhile, the company’s upgradation of four lane bridge from km 406 to km 381 near Kota (RJ-4) on NH-76 in Rajasthan is nearing completion. The company is implementing project in JV with ITD Cem.