Ispat's Dolvi project incurs further cost overrunIllustrative image – not actual.

The three million tonne per annum hot rolled coils project of Ispat Industries at Dolvi in Raigarh district of Maharashtra, is facing yet another cost overrun. The latest cost overrun has increased project cost by Rs.700 crore, from around Rs.6,500 crore to Rs.7,206 crore.

 

The original project cost (estimated two years ago) of the project’s phase II, which will expand capacity from 1.5 million tonnes to 3 million tonnes, was Rs.4,590 crore. This escalated to Rs.6,500 crore at the end of 2000-01. Phase II has been delayed by over two years now. Phase I (with a capacity of 1.5 million tonnes) was commissioned in April 2000.

 

The promoters are planning to pump in Rs.312 crore as additional capital, to part-finance the project. This would be done through subscription to equity shares to the extent of Rs.245 crore and to preference shares of Rs.67 crore from promoters and others.