Illustrative image – not actual.The Ispat Group and financial
institutions are reportedly working out a proposal to expedite the
implementation of the second phase of the three million tonne steel plant
coming up at Dolvi in Maharashtra.
Part of the project envisaged the
setting up of a captive power plant of 367 MW through a subsidiary, Ispat
Energy Ltd. The capacity of this proposed plant is now being scaled down to 230
MW. This exercise is expected to save around Rs.500 crore in capital
expenditure. This would also result in lowering the exposure of financial
institutions to the project. IEL is also toying the idea of using coal as
feedstock as against naphtha and LNG envisaged earlier. IEL proposes to use gas
from the steel plant to feed 80 MW of the power plant’s capacity while 150 MW
would run on coal.
It may be mentioned that Enron, which
was to pick up 49 per cent stake in IEL, has now decided against the proposal.
Meanwhile, the second phase (1.5
million tonnes) of the 3 million tonne steel project is expected to be
completed by mid-2001, after a delay of two years. The first phase was
commissioned in June 1998. The project cost has risen to Rs.6,587 crore from
the earlier envisaged Rs.4,845 crore.