Ispat reviews power projectIllustrative image – not actual.

The Ispat group is reportedly undertaking a review of its 367 MW power project at Dolvi in Raigarh district of Maharashtra. This follows financial institutions' refusal to meet the Rs.100 crore shortfall in project cost caused by Enron's withdrawal from the project.

 

FIs have questioned the viability of the Rs.1,432 crore project and have demanded that a fresh feasibility study be undertaken by ICICI.

 

The Ispat group is reworking the capacity of the project and planning to curtail capacity to the power requirement of the group’s steel plant at Dolvi, at around 250 MW. The original plan was to sell 90 MW of the power generated to the State electricity grid.

 

Ispat is also considering a change in fuel from LNG to coal, on account of the uncertainty of LNG supply.