Illustrative image – not actual.Ispat Industries has received a Rs.180 crore loan from financial institutions (FIs) to part-finance the second phase of its three-million tonne per annum hot rolled coil project at Dolvi in Raigarh district of Maharashtra.
This is the first tranche of a Rs.700 crore loan sanctioned by FIs. A portion of the loan is also to be utilised by the company to repay its outstanding debt.
The second phase of the project is
expected to be commissioned by June 2001. It was originally scheduled to be completed
by September 2000, but was delayed on account of non-disbursement of loan. FIs
had insisted that the company comply with all the pre-disbursement conditions,
which included the retrieval of Rs.417 crore that the company had invested in
non-steel businesses.
For the second phase, SMS Demag of
Germany will install the second twin shell electric arc furnace at the unit. The
project also envisages the setting up of a 146 metre long second tunnel furnace
and a caster unit. In order to overcome the shortage of oxygen at the unit, the
company has decided to install a 1,260 tonne per day oxygen plant at a cost of
Rs.100 crore.
The first phase of this project
was completed way back in June 1998.