Illustrative image – not actual.Ispat Industries is likely to put some of its delayed projects back on track.
The projects include a coke oven plant at a cost of Rs 1,100 crore, a Rs 490 crore power plant and mining projects at an outlay of Rs 120 crore.
The 110 MW power plant is likely to be commissioned by June 2011 while the coke oven plant will be completed in June 2012. Both the plants are to be located at Dolvi in Maharashtra. In the coke oven project, Ispat is expected to hold 26 per cent of the equity and in the power plant around 85 per cent.
The iron ore project at Damkodwadvi is slated to commence production from 2011 while the land for the coking coal project in Madhya Pradesh has just been allotted.