Irrigation projects to be commissioned in phasesIllustrative image – not actual.

The Union Ministry of Water Resources reportedly proposes to commission large and medium irrigation projects in phases, in order to reduce the adverse impact of spill-over costs.

 

According to a Planning Commission study, the spill-over cost of 162 large and medium irrigation projects, along with ERM (extension, renovation and modernisation projects), is around Rs.1,36,133 crore at the beginning of the Ninth Plan, while outlay for the Plan period is Rs.42,974 crore.

 

According to a report prepared by the National Commission for Integrated Water Resources Development Plan (NCIWRDP), 1999, the funds required for completion of ongoing projects would be to the tune of around Rs.70,000 crore in the Tenth Plan and Rs.1,10,000 crore in the Eleventh Plan. However, on account of huge spill-over costs, there may be no scope for new projects in the next two Plan periods.