Illustrative image – not actual.The Union Ministry of Water
Resources reportedly proposes to commission large and medium irrigation
projects in phases, in order to reduce the adverse impact of spill-over costs.
According to a Planning Commission
study, the spill-over cost of 162 large and medium irrigation projects, along
with ERM (extension, renovation and modernisation projects), is around Rs.1,36,133
crore at the beginning of the Ninth Plan, while outlay for the Plan period is Rs.42,974
crore.
According to a report prepared by the
National Commission for Integrated Water Resources Development Plan (NCIWRDP),
1999, the funds required for completion of ongoing projects would be to the tune
of around Rs.70,000 crore in the Tenth Plan and Rs.1,10,000 crore in the Eleventh
Plan. However, on account of huge spill-over costs, there may be no scope for
new projects in the next two Plan periods.