IRCON has completed 100 km track linking out of 372 km stretch entrusted by the Dedicated Freight Corridor Corporation of India (DFCCIL) between Vaitarna-Sachin sections by using imported new track construction machine.
It has been possible by the dedicated team of IRCON despite the lockdown due to COVID-19 and insufficient resources.
IRCON is the first PSU which owns NTC machine that was imported by IRCON from the US for the purpose of this project.
In July 2021, IRCON has completed highly ambitious task of installation and completion of precast double shell box with a segment size of 16 x 10 mtr at Valsad, South Gujarat in record time of 20 days power block.
IRCON also completed commissioning of 74 km section from Kharsia to Dharam Jayagarh on 21 June 2021 through its SPV - Chhattisgarh East Rail (CERL). Thus, CERL is the only SPV to commission section of railway line through PPP mode.