Illustrative image – not actual.IRB Infrastructure Developers is likely to achieve financial closure for its Tumkur-Chitradurga road project in Karnataka by October 2010.
The company is likely to mop up Rs 750 crore of debt from a consortium of three financiers led by Infrastructure Development Finance Company (IDFC) by October 2010 for the Rs 1,200-crore road project. The remaining Rs 450 crore is to be funded through internal accruals.
The six-laning project envisages designing, building, financing and operation of the Tumkur-Chitradurga section of NH-4 for 114 km in Karnataka. The BOT project has a concession period of 26 years. In May 2010, IRB had bagged the road project from the NHAI.
Related Links:
Project profile
