IRB Infra executes concession agreement with NHAIIllustrative image – not actual.

IRB Infrastructure Developers’ wholly-owned subsidiaries executed concession agreement with the National Highways Authority of India for two hybrid annuity projects under NHDP Phase IV in Tamil Nadu.

IRB PS Highway will undertake four-laning of Poondiankuppam to Sattanathapuram (design ch 67.000 km to 123.800 km) section of NH-45A. The company quoted a bid project cost of Rs 2,169 crore with operation and maintenance cost of Rs 1.08 crore in the first year.

The 56.80 km long road project has a construction period of 730 days and operation period of 15 years.

IRB PP Project will undertake four-laning of Puducherry (29.000 km) to Poondiyankuppam (67.000 km) section of NH-45A (new NH-32). The company quoted a bid project cost of Rs 1,296 crore with operation and maintenance cost of Rs 2.07 crore for the first year.

The 38 km long road project will be executed in 730 days with operation period of 15 years.