IRB Hapur Moradabad Tollway executes concession agreementIllustrative image – not actual.

IRB Infrastructure Developers, a wholly-owned subsidiary IRB Hapur Moradabad Tollway, has executed concession agreement with the National Highways Authority of India (NHAI) for a road project in Uttar Pradesh.

The scope of work includes six-laning of Hapur bypass to Moradabad section, including Hapur bypass from 50.000 km (design ch 50.000 km) to 148.277 km (design ch 149.867 km) of NH-24 (new NH-9) in Uttar Pradesh on design, build, finance, operate, transfer (DBFOT) basis under NHDP Phase-V project.

The concession period is 22 years, including construction period of 910 days. The total cost of the project is Rs 3,421 crore.

The company will get the tolling rights of the project from the appointed date.

It has offered a premium of Rs 31.5 crore to NHAI to be payable from fourth year from the appointed date in terms of concession agreement.

 