Illustrative image – not actual.Iranian Offshore Engineering & Construction Co has won a $30 million contract for constructing an oil terminal for Indian Oil Corporation at Paradip Port.
The project scope involves construction of a floating crude oil terminal along with a 20 km (48" dia) pipeline. Crude carriers will transfer (at sea) oil to the terminal through the pipeline.
Work on the project would begin in September 2005 and is targeted for completion before December 2005, it is learnt.
The floating oil terminal is part of IOC's Paradip greenfield refinery project. Work on the refinery, which might undergo a change in project scope, is scheduled to begin in December 2006 with completion targeted for March 2010.
Also See:
IOC to decide revised Paradip refinery project in Sep (10-May-05)