Illustrative image – not actual.Indian Oil Corporation's (IOC) ongoing pipeline projects, viz. the Haldia-Barauni pipeline and the Salaye-Panipat pipeline, are expected to be completed within three years time.
In the case of the 437 km Haldia-Barauni pipeline, work relating to laying 230 km of the pipeline has already been completed, while the designing of the 1,400 km Salaye-Panipat pipeline project has been completed.
These two pipeline projects form part of the 2,000 km of new pipeline that were proposed to be laid during the Ninth Plan. Out of the total 8,000 km long pipeline network, IOC owns and operates pipelines measuring a total length of 6,453 km.
IOC pipeline projects for the Ninth Plan are estimated to cost Rs.8,000 crore.