Illustrative image – not actual.Indian Oil Corporation’s plan of expanding the capacity of its Barauni Refinery in Bihar from 4.2 million tonnes per annum (tpa) to 6 million tpa is facing a cost overrun of Rs.160 crore. This is mainly on account of constraints in the procurement of equipment.
The cost of the expansion programme is now estimated at Rs.1,963 crore as against Rs.1803 crore earlier.
IOC is also expecting a delay in the project completion schedule – from February 2002 as envisaged earlier to May 2002, now.
Meanwhile, IOC’s Panipat Refinery expansion plan (from 6 million tpa to 12 million tpa) is also facing a time overrun of four months.