Illustrative image – not actual.Indian Oil Corp is reviewing its 9 million tonne per annum Paradeep refinery project following time and cost overruns. The project is cost has gone up by more than 20 per cent and its implementation has been delayed by 18 months.
The
project cost has gone up to Rs.9,982 crore as against Rs.8,270 crore approved
by the government in July 1998, while the project implementation has been
delayed for more than one-and-a-half years because of the withdrawal and
subsequent restoration of incentives by the Orissa state government. The
project received a setback when the state government, contrary to its earlier
order of December 1998/ August 1999 for exemption and deferment of sales tax on
finished products from the products from the project, withdrew the incentives
in February 2000.
The
project faced problems from the start with Hindujas and Kuwait Petroleum Corp
withdrawing from the project, later Indian Oil proposed to start the project on
its own.