Illustrative image – not actual.Indian Oil Corporation (IOC) has finalised
plans to convert its Kandla-Bhatinda product pipeline into crude pipeline. This
project is estimated to cost Rs.1,500 crore and would be completed in about 30
months.
According to Mr A M Uplenchwar, IOC director,
pipelines, this project is expected to help IOC save around Rs.700 crore as
laying an additional pipeline for crude would cost more than Rs.2,000 crore.
It may be mentioned that the Kandla-Bhatinda product
pipeline, which was used for transporting petroleum products to the north, was
reportedly, underutilised after the commissioning of IOC’s Panipat (Haryana) and
Mathura (Uttar Pradesh) refineries. Further, Hindustan Petroleum Corporation is
also setting up a 9 million tonne, Bhatinda refinery in Punjab.
On the other hand, IOC needed to transport imported
crude to its refineries to fully utilise their capacities. Transporting crude
through rail or by road would be uneconomical. In fact, the need for
transporting crude through pipeline became more acute after the corporation
decided to increase the capacity of its Panipat refinery from 6 million tonnes
to 12 million tonnes.
IOC has decided to extend the Kandla-Bhainda pipeline
to Mundra in Gujarat where large vessels could be unloaded for the Panipat
refinery. A single point mooring facility will be provided at Mundra.
Meanwhile, IOC has decided to lay a spur pipeline
from its Koyali refinery in Gujarat to Sidhpur (Gujarat), and from Sidhpur to
Jaipur (Rajasthan) connecting it with the Kandla-Bhatinda pipeline for the transportation
of products.