IOC to commission Chennai-Trichy-Madurai product pipelineIllustrative image – not actual.

Indian Oil is likely to commission the Rs.500 crore Chennai-Trichy-Madurai product pipeline network of 683 km. and laid through 11 districts of Tamil Nadu. The product will be received through the pipeline by mid-March 2006 at Trichy terminal, which will be commissioned by 1 April 2006.

The diesel through the pipeline has already been received through the Madhurai terminal and has reached the Sankari depot. The pipeline constructed using state-of-art technology is to ensure uninterrupted supply of diesel, kerosene and petrol.

The capacity of Phase-I of the project is expected to be 1.8 million tpa in the Chennai-Asanur sector, 0.8 million tpa in the Asanur-Sankari branch line. The proposed capacity will be increased in Phase-II to 2.3 million tpa in the Chennai-Asanur sector and 1.3 million tpa in the Asanur-Sankari branch line.

Also see:

IOC to build Chennai-Trichy-madhurai product pipeline alone (19-Aug-02)

← All latest storiesBack to top →