Illustrative image – not actual.Indian Oil Corporation (IOC) is set to begin work on the Chennai-Tiruchi-Madurai pipeline in the third week of August 2004. The 683-km long, cross-country petroproducts pipeline is estimated to entail an investment of Rs.400 crore.
The contracts for laying the main pipeline, parallel telecommunication and optic fibre cables have been awarded. Essar Constructions has been selected for laying the main pipeline. The coated pipes are being supplied by Maharashtra Seamless and Surya Roshini.
The route of the pipeline is tabulated below:
| Route | Diameter (inches) |
Length (km) |
| Chennai-Asanur | 14 | 256 |
| Asanur-Tiruchi-Madurai | 10 | 270 |
| Asanur-Sankari Branch Pipeline | 12 | 157 |
The pipeline would traverse through 13 railway crossings, 15 national highway crossings and two major rivers -- River Coleroon and River Cauvery. The Horizontal Directional Drilling (HDD) method is being adopted to negotiate the rivers.
The pipeline, when completed in July 2005, would facilitate the evacuation of petroleum products from Chennai Petroleum Corporation's refinery in Chennai.