Illustrative image – not actual.Indian Oil has shelved its plan to set up an LPG pipeline network connecting its major refineries owing to lack of throughput. The project may be revived later, following completion of the Paradip refinery project in Orissa.
Plans are, however afoot to connect Kolkata and Hyderabad airports through ATF pipelines and IOC has already decided to commission ATF pipelines to Chennai and Bangalore airports.
Its decision to set up the first ever LPG pipeline from Panipat refinery in Uttar Pradesh to Jalandhar in Punjab, IOC had commissioned a study to explore the possibility of setting up an LPG pipeline across the country to reduce freight costs. It is learnt that, the 275 km Panipat-Jalandhar pipeline will reduce freight cost by 30-40 per cent. Studies, however, point out that the existing throughputs at major refineries like Koyali, Haldia or Chennai (CPCL) will not be sufficient to make the pipeline network commercially viable.
Also See:
IOC seeks concessions for buying Cairn's Rajasthan crude (31-Jan-07)