Illustrative image – not actual.Indian Oil Corporation is seeking $60
million (Rs.288 crore) as loan from the US Exim Bank for the company’s proposed
petrochemical complex coming up at Panipat in Haryana.
IOC is setting up a Rs.5104 crore
integrated paraxylene-PTA (purified terephthalic acid) project within the
company’s Panipat refinery in Haryana. The plant will have a capacity to annually
produce 3,50,000 tonnes of paraxylene (PX) and 5,25,000 tonnes of PTA.
The project was originally budgeted to
cost Rs.4,228 crore and was targeted for completion in August 2004. By present
thinking however, the project would cost Rs.5,104 crore (cost escalation of 876
crore or 20 per cent) and is scheduled for completion by July 2005. IOC is
trying to reduce the capital cost to around Rs.4,556 crore. The main reason for
the delay in the project was IOC’s decision to relocate the project to within
the Panipat complex, and the subsequent integration of offsite facilities.
The construction contract for the PTA
unit has been awarded to Larsen & Toubro, while that of the PX unit is being
finalized. Meanwhile, IOC selected UOP of USA as the technology licensor for
the PX unit. The technology transfer fee is reported to be $21.57 million.
IOC has meanwhile decided to integrate
the project with the Panipat refinery expansion project, in order to bring
about greater economies of scale. The project is being implemented in five lumpsum
turnkey packages with Engineers India Ltd as the project management consultant.
The project was earlier conceived as a
joint venture with equity participation from Petronas of Malaysia and ONGC.
However, none of these plans fructified. IOC, however, has plans to introduce a
strategic partner in the project, at a later date.